| Nature of project: |
|
Marine Construction & Dredging Project |
| Country: |
|
Israel |
| Location: |
|
Ashkelon, Eilat-Ashkelon Oil Pipeline Ltd. |
| Execution period: |
|
Nov. 2000 – Dec. 2001 |
| Client: |
|
Eilat-Ashkelon Oil Pipeline Ltd. |
| Description: |
|
Breakwater reconstruction – closure of
the existing Northern entrance and opening a new Western one.
Construction of 100 m. length tugboat quay. The works include among other:
- 130,000 m³ of Maintenance Dredging for the approach channel and Israel Electric Co.
turning basin.
- 30,000 m³ Capital Dredging Works
- 20, 000 m³ Land Reclamation for berth construction
- 50, 000 m³ Rock Movement for breakwater construction/reconstruction (includes
9 to 0,2 ton stones)
- 400 ton Arbed Steel sheet pile driving, 50 ton steel tie rods.
- 2,200 m³ Concrete and Reinforced Concrete works
|
| Contract value in USD: |
|
4,000,000 |
| Company Status: |
|
Main contractor |
| |
|
|